Aris Mining confirms extended operational timeline of Toroparu gold project in PFS

Aris Mining confirms extended operational timeline of Toroparu gold project in PFS

Canadian gold miner Aris Mining Corporation has confirmed in a prefeasibility study (PFS) on the Toroparu gold project, in Guyana, its potential for a large-scale and long-life openpit development producing 5.6-million ounces of gold over a 29-year processing period, including 21 years of mining.

With the PFS complete and the large-scale mining licence application under review, Toroparu is progressing through pre-development activities.

Aris aims to make a construction decision early in 2027, subject to receiving the large-scale mining licence and other necessary approvals.

The PFS contemplates a 32-month construction period and supports Toroparu’s potential to become a major new long-life gold mine in Guyana. The PFS also underscores Toroparu’s status as a cornerstone asset within the portfolio as Aris executes its strategy to become a major gold producer in South America.

Some of the key findings of the PFS include an extended operating life through planned treating of lower-grade tonnes toward the end of the mine life, whereas the 2025 preliminary economic assessment (PEA) on the project envisioned this as waste; and the use of contract mining instead of the owner-operated, equipment-leasing model contemplated by the 2025 PEA.

The PFS confirms planned average gold production of 291 000 oz/y over the first five years and 258 000 oz/y during the main pit operations, or first 17 years, followed by 103 000 oz/y in the later life of the mine and stockpile processing operations – years 18 to 29.

The Toroparu project will require an initial capital commitment of $1-billion, but is poised to generate average yearly earnings of $588-million during the main pit operations. The project’s after-tax net present value (NPV) is estimated at $2.8-billion, its internal rate of return (IRR) 31.5% and its payback period 2.2 years from the start of operations – at base case prices of $3 600/oz of gold, $50/oz of silver and $5/lb of copper.

The NPV and IRR increase to $3.8-billion and 37.8%, respectively, at a gold price of $4 200/oz, and decrease to $1.8-billion and 24.3%, respectively, at a gold price of $3 000/oz.