Mining News Pro - Rio Tinto flagged on Friday a cost increase of $300 million for the ongoing expansion of its massive Oyu Tolgoi copper-gold mine in Mongolia.
The world’s second largest miner said the cost and schedule reforecast, completed in June, now pegs the total project cost estimate at $7.06 billion, almost $1.8 billion higher than its original estimate in 2015.
The company blamed the rise on skilled labour supply constraints caused by covid-19 and noted the new estimate, under review by Oyu Tolgoi’s board, assumes there are no further disruptions.
Rio Tinto currently controls and operates the mine, located 550 km (342 miles) south of Mongolia’s capital Ulaanbaatar, through its 66% stake in Canada’s Turquoise Hill Resources (TSX, NYSE: TRQ). The government of Mongolia owns 34%.
The mining giant is currently trying to buy all the shares it doesn’t already own in Turquoise Hill.
Rio’s chief executive Jakob Stausholm has said he believes the acquisition would simplify the ownership structure, and further strengthen the company’s copper portfolio.
The offer followed an agreement between the miner and the government of Mongolia to complete the long-delayed underground expansion.
That deal saw Rio agree to write off $2.4 billion in loans and interest used by Ulan Bator to fund its share of the development costs.
There was no update on the proposed C$34.00 per share buyout.
Turquoise Hill said in a separate statement it expected its portion of total operating cash costs at Oyu Tolgoi to increase by $50 million for this year. It means they are now expected to be in the range of between $850 million and $925 million, higher than previous guidance of $800 million to $875 million.
This was due to higher royalties and price inflation for key raw materials, especially fuel and the lower deferred stripping, the firm said.
Three-year delay and counting
The ongoing expansion of Oyu Tolgoi has been plagued by delays and costs overruns, which have triggered the Mongolian government’s ire to the point of threatening to revoke the 2009 investment agreement, which underpins the mine development.
First production, initially expected in late 2020, was rescheduled for October 2022 and later to the first half of 2023.
Rio Tinto said on Friday that technical progress has been hindered, with shafts 3 and 4 now expected to be commissioned in the first half of 2024, 15 months later than what the company estimated in 2020.
Oyu Tolgoi is Rio’s main copper growth project. Once completed, the underground section will lift production from 125,000–150,000 tonnes in 2019 to 560,000 tonnes at peak output, which is now expected by 2025 at the earliest.
According to the miner, this would make it the biggest new copper mine to come on stream in several years and, by 2030, the operation would be the world’s fourth largest copper mine.
Short Link:
https://www.miningnews.ir/En/News/621755
Copper futures in New York rallied to a record high after a short squeeze that’s prompted a scramble to divert metal in ...
A Native American group said on Tuesday it will take its fight against Rio Tinto’s proposed Arizona copper mine to the ...
Teck Resources Ltd expects to generate annual earnings before interest, depreciation, tax and amortization (EBITDA) of ...
The state-run Chilean Copper Commission (Cochilco) will soon revise its copper price outlook, which will be considerably ...
Chilean mining giant Codelco is still working to meet its estimated output for the second quarter, CEO Ruben Alvarado ...
Indonesia’s outgoing government has added 16 programs to its list of strategic projects that will receive state support, ...
Truck drivers in Chile staged protests Monday in the mineral-rich north of the country and around the capital Santiago, ...
Democratic Republic of Congo’s government has lifted a suspension order on a Congolese copper and cobalt operation ...
Peru’s copper production came in essentially flat for March at about 219,000 metric tons, government data showed on ...
No comments have been posted yet ...