Mining News Pro - An expert group reviewing the cause of a $1.4 billion cost overrun at a Mongolian mine run by Rio Tinto said it was caused by the miner’s mismanagement, the Wall Street Journal reported on Monday, citing a report.
Costs to expand the Oyu Tolgoi mine, Rio’s biggest copper growth project, have ballooned up to $6.75 billion from Rio’s original budget of $5.3 billion in 2016, and this has led to a friction over funding with Turquoise Hill.
Turquoise Hill, in which Rio has a 50.8% stake, owns 66% of Oyu Tolgoi, one of the world’s largest-known copper and gold deposits. The rest is held by the Mongolian government.
The report, which was commissioned by the owners of the copper project, said the cost overrun was not due to unfavorable rock conditions as blamed by the one of world’s largest miner, the WSJ reported.
“This confidential report will be considered by the OT (Oyu Tolgoi) Board and Rio Tinto will engage with the OT Board as soon as we have had the opportunity to review the report in detail,” Rio Tinto said in an emailed statement.
There was no evidence that the quality of the rock and general ground conditions were significantly different to that forecast by the miner’s owners in 2016, according to the report.
The WSJ report said the U.S. Securities and Exchange Commission and British regulators were looking into the matter.
Turquoise Hill Resources did not immediately respond to a Reuters request for comment.
Short Link:
https://www.miningnews.ir/En/News/615270
Copper futures in New York rallied to a record high after a short squeeze that’s prompted a scramble to divert metal in ...
A Native American group said on Tuesday it will take its fight against Rio Tinto’s proposed Arizona copper mine to the ...
Teck Resources Ltd expects to generate annual earnings before interest, depreciation, tax and amortization (EBITDA) of ...
The state-run Chilean Copper Commission (Cochilco) will soon revise its copper price outlook, which will be considerably ...
Chilean mining giant Codelco is still working to meet its estimated output for the second quarter, CEO Ruben Alvarado ...
Truck drivers in Chile staged protests Monday in the mineral-rich north of the country and around the capital Santiago, ...
Democratic Republic of Congo’s government has lifted a suspension order on a Congolese copper and cobalt operation ...
Peru’s copper production came in essentially flat for March at about 219,000 metric tons, government data showed on ...
Oxford Economics Australia has released data showing mine maintenance spending may be hitting its peak. But what does it ...
No comments have been posted yet ...