Mining News Pro - Gold Fields and Gold Road Resources have faced more than a month’s delay in the construction and commissioning of the Gruyere joint venture project in Western Australia.
According to Mining News Pro - The Gruyere partners were not able to commission the ball mill within the contractual completion dates. They now expect to commence the commissioning early in the September quarter.
As a consequence, gold production for the year has been lowered to between 75,000 to 100,000 ounces, down from 100,000 to 120,000 ounces previously.
The operation’s all-in sustaining costs (AISC) will also likely be higher than the previous guidance of between $1050 and $1150 an ounce.
“The delay in construction and commissioning is disappointing, however, the areas of the plant currently commissioned are performing strongly,” Gold Fields executive vice president Stuart Mathews said.
“Additionally, mining continues to track ahead of plan and mined tones are closely aligned to reserve and grade control estimates, which sets Gruyere up for sustainable production once commissioning and ramp up have been completed.”
Gruyere has around two million tonnes of ore mined and stockpiled to date, with gold grades that are estimated to align closely to projections.
The project is on track to deliver first gold in the current quarter, in line with guidance following the commissioning of the crusher and semi-autogenous grinding (SAG) mill this year.
“As a global Tier 1 gold mine, the project remains within cost guidance and we are confident of a successful ramp-up to nameplate capacity and the long-term performance of the operation,” Gibbs said.
The project’s mine-life average yearly production is estimated at around 300,000 ounces a year, with AISC over a 12-year life averaging around $1025 an ounce.
Gold Road’s balance sheet “remains strong and is positioned to manage any delays”, according to Gold Road managing director Duncan Gibbs.
The JV partners also continue to provide support to the engineering, procurement and construction (EPC) contractor, Gibbs added.
Short Link:
https://www.miningnews.ir/En/News/388578
China’s central bank paused gold purchases to its reserves in May, when spot gold prices hit a record high, after 18 ...
Gold fell the most in more than two years as surprise strength in a key US jobs report dashed hopes that the Federal ...
Global physically backed gold exchange traded funds (ETFs) attracted their first inflows in May after a year, powered by ...
Ivory Coast’s gold output hit a record high in 2023, helped by the opening of new mines, and will continue to grow ...
Glencore Plc is considering selling its stake in Kazakh mining company Kazzinc amid interest from potential buyers in ...
State revenue from gold mining companies in Mali fell 26% last year, hit by lower taxes, a document from the west ...
Net purchases of gold by global central banks rose to 33 metric tons in April from a revised net buying of 3 tons in ...
Probe Gold is looking to raise more than C$15 million ($11 million) via a private placement led by Beacon Securities and ...
Money managers became the most bullish on gold in more than four years as prices surged to a fresh record earlier this ...
No comments have been posted yet ...