Mining News Pro - Rio Tinto is challenging the findings of an independent review into $1.4 billion in cost overruns and delays at the Oyu Tolgoi mine in Mongolia, restating the project’s troubles were caused by unpredictable geology issues.
The Independent Consulting Group’s (IGG) report concluded last month that poor management was the main reason the mine’s underground expansion has run into problems affecting its cost and timeline.
While Rio has said it understands stakeholders’ frustration it believes the review did not sufficiently recognize the full impact of weaker than expected rock conditions, which forced the mining giant to redesign the project.
Costs to expand the Oyu Tolgoi mine, Rio’s biggest copper growth project, have ballooned up to $6.75 billion from Rio’s original budget of $5.3 billion set in 2016, and this led to friction over funding with mine operator Turquoise Hill (TSX, NYSE: TRQ). The firms finally reached an agreement in April.
Canada’s Turquoise Hill, in which Rio has a 50.8% stake, owns 66% of Oyu Tolgoi. The rest is held by the Mongolian government.
“We are concerned that the report takes a narrow view of what constitutes geotechnical impacts on the project,” Rio’s head of projects Mark Davies said in a letter to Mongolia’s justice minister Khishgee Nyambaatar, quoted by the Financial Times.
The message, sent last week, said other issues, such as fitting out a key access shaft, had also affected the project. It added those matters were “transparently reported” to its partners.
Davies said the fact that 96% of the workforce was Mongolian, which is “far higher” than initially planned also weighed on the project.
“The investment in the national workforce did have an impact on project costs and schedule; more than the ICG recognizes,” the letter said.
Rio Tinto has repeatedly said the underground expansion of Oyu Tolgoi is its most important growth project. First production, initially scheduled for late 2020, is now expected in October 2022.
Once completed, the mine’s underground section will lift production from 125,000–150,000 tonnes in 2019 to 560,000 tonnes at peak output, which is now expected by 2025 at the earliest. This would make it the biggest new copper mine to come on stream in several years.
Short Link:
https://www.miningnews.ir/En/News/616729
Barrick Gold Corp.’s chief executive officer says the gold miner will continue to host virtual-only annual general ...
China’s copper producers are planning to export up to 100,000 metric tons of metal, the largest volume in 12 years, ...
A takeover of Anglo American Plc would need to be pitched at more than £30 ($37.6) per share, a higher price than BHP ...
Barrick Gold is not interested in bidding for Anglo American, which last week received a $39 billion takeover offer from ...
BHP Group can’t cherry pick Anglo American assets without paying a hefty premium, Anglo investors told Reuters, ...
Anglo American faced calls from shareholders on Monday to detail plans for improving its value in order to fend off ...
Copper slipped after initially extending gains above $10,200 a ton as traders turned their attention to demand ...
Glencore expects profit at its trading division this year to be at the top end of its long-term annual guidance, in an ...
Top copper producer Codelco reported a decline in quarterly output due to lower quality ore at its aging Chilean mines — ...
No comments have been posted yet ...