Torex Gold to spend up to $440 million on Media Luna project
Friday, February 10, 2023 - 19:24:11
Mining.com
Delivering a first quarter update, the Canadian miner noted that total upfront expenditures tied to Media Luna were unchanged at $874.5 million.

Chief executive officer Jody Kuzenko said the project was 15% complete by the end of 2022, adding that work was expected to ramp-up significantly in the months ahead.

She added that 2023 is shaping up to be the peak year of spending in Media Luna, which is part of the company’s Morelos Complex.

The Toronto-based company said last month it anticipated production of 440,000 to 470,000 ounces of gold this year, up from the 420,000-460,000 ounces range forecast in the company’s three-year outlook released in March 2022.

Torex currently operates the 100% owned Morelos property, covering an area of 29,000 hectares in the Guerrero gold belt of Mexico. 

The complex hosts the El Limón Guajes (ELG) mine complex, which started commercial production in 2016, as well as the Media Luna deposit, a processing plant and related infrastructure.

Media Luna, located 7km from ELG, is expected to produce 280,000 ounces of gold annually over an 11.75-year initial mine life, plus 34.8 million pounds (15,800t/y) of copper per year and 1.3 million annual ounces of silver.